Three and recommend plunger pump safety operation procedures:
1.Check whether the oil level of the oil tank of the reducer, the oil level of the three-plunger high-pressure pump and the water level of the emulsion tank are at the specified oil level and water level.
2.Check whether the safety valve, pressure gauge, water level gauge and liquid level indicator are sensitive and correct; check the pressure gauge and safety valve once a year, and drain the safety valve regularly to prevent the valve core from sticking and blocking the valve hole.
3.Check whether all parts of the pump, all valves, solenoid valves, pipes, etc. are in good condition, and there must be no water leakage, air leakage or oil leakage. Check whether the zero electric (ground) line is firm and reliable. When the pump stops running for more than one week, please measure the insulation of the main motor. Good.;Check whether the contact signal of the hydraulic press is correct and reliable.
4.When opening and closing the valve, please stand on the side of the valve stem and rotate it slowly.
5.Do not leave the working position while working, and closely monitor whether the control instruments and water level indicators are normal. If the wrong water level occurs, take immediate action, every10-15Check all equipment every minute and record the running status every hour. Liquid temperature must not exceed60°C, the cooling water temperature shall not exceed40°CThe motor temperature shall not exceed the rated temperature rise.

6.The plunger pump should maintain a certain oil level, and should usually be kept at one-tenth to seven-tenths of the oil-immersed surface. If the oil is insufficient, it should be filled in time to ensure the normal operation of the equipment.
7.If overpressure is found, immediately pull out the pressure plug and cut off the main power supply. After the water level drops to normal, notify the hydraulic press to stop working. After the repair returns to normal, you can continue to work.
8.Check the water (gas) storage tank, air valve and air pipe for leaks with soapy water. If dew and frost (water), it indicates that the leakage is serious and should be repaired in time. To defrost, disable open flames.
9.Active protective railings shall be provided around the system. Do not disassemble or move during normal operation. Non-operators are not allowed to enter during operation.
10.The system is a high-pressure working equipment, and the management and operation of the corresponding containers must strictly comply with relevant regulations.
11.All exposed rotating parts in the system must be equipped with safe and reliable protective covers. After removing the protective cover, it is forbidden to start the machine. Under special circumstances, detailed and strict supervision and preventive measures must be taken.